How does a construction payment schedule work?
A construction payment schedule lists what the client pays and when. A deposit funds the start of the job. Monthly invoices bill work as it progresses. Deposit credits reduce later amounts due, so the client pays the budget once. A contractor payment schedule in the contract tells the client how much money to have ready each month.
Worked example: a $500,000.00 renovation over 10 months
| 1 | Upfront depositBudget × 10%, capped at $150,000.00 | $500,000.00 × 10% =$50,000.00 |
|---|---|---|
| 2 | Remaining to billBudget − deposit | $500,000.00 − $50,000.00 =$450,000.00 |
| 3 | Invoice for month 1Work billed in the month − deposit credit | $78,000.00 − $0.00 =$78,000.00 |
| 4 | Invoice for month 10Work billed in the month − deposit credit | $36,000.00 − $15,333.33 =$20,666.67 |
How it works
Choose renovation or new construction, then enter the total client budget and the build length in months. The calculator sets one deposit, spreads the work across the months, and applies deposit credits to the later invoices. The chart and the table show each amount, and the total due always equals the budget.
When to use it
Use it before you sign the contract, to show the client what each month will cost. For lender draws and interest, use the construction loan calculator. To prepare a client bill, use the construction invoice template for a fixed price or the cost-plus invoice template for cost plus a fee.
Deposits and deposit credits
The deposit is money the client pays before work starts. It is not an extra charge. Each deposit credit lowers a later invoice by the same amount, until the deposit balance is zero. On a cost-plus construction contract, the monthly amounts move with actual cost, so treat the schedule as a plan and update it as the job changes.
Payment schedule or cash flow
This schedule shows the money a client owes each month. It does not show what you pay out, or when each payment arrives. To see what payment terms do to the cash in your business, use the construction cash flow calculator.
How much does it cost to build a house?
In NAHB’s 2024 survey, sampled homes averaged $428,215 in construction costs and $665,298 in total sales price. The sales price also included the lot, financing, overhead, and builder profit. These are survey averages, not a local quote. Read the NAHB cost study.
Your house building cost depends on location, size, site conditions, and finishes. Start with a builder’s estimate, then enter the client budget above to see a monthly construction payment schedule. The $1.5 million new-home example is a custom-home scenario, not a national average.
Common mistakes
- A deposit with no plan to credit it. State in the contract when each credit applies, so the client knows what the final invoices will be.
- Equal monthly payments on a job that does not spend equally. Work billed follows the work done, and most homes bill more in some months than in others.
- A schedule that ignores the lender. If a loan funds the job, match your invoice dates to the lender's draw dates.
- No update after a change. A signed change order changes the budget, so run the schedule again with the new total.